Four of the operating rooms in the 2nd floor surgery suite at St. Joseph’s Medical Center needed an upgrade.

Barden Electric, Inc. took the job on as the design-build general electrical contractor. BEI conferred with the manufacturer, the hospital, and a TMAD structural engineer to create the necessary plans, and get them OSHPD approved and permitted.

The work would have to be done off hours and completed over a single month, but BEI pushed the tight schedule through on each 6-day project: demolishing and disposing of the old system, welding the new supporting infrastructure in place, carrying out deputy inspections, coordinating installation with the manufacturer, obtaining OSHPD sign-off, and turning over the OR to the hospital for bio-med all without disrupting a month’s worth of scheduled surgeries.